What’s Happening Now?

 

Goleta Valley Cottage Hospital (updated March 2014)

  • Q4 2014 — Hospital Completion
  • Q1 2015 — Patient Move
  • mid 2015 — Demolition of existing hospital
  • late 2015 — Completion of Parking Lot

Santa Ynez Valley Cottage Hospital (updated July 2013)

  • 2013 — Completion of Laboratory and new Emergency Department areas
  • 2013 — Completion of Surgery areas
  • Q1 2014 — Completion of new entrance canopies, Admitting and balance of existing ED remodel

Santa Barbara Cottage Hospital

  • June 2013–July 2014 — Construct ‘link building’ creating pathway from the new buildings and Centennial Wing to the South and East wings
  • September 2013–July 2014 — Build new conference rooms on the first floor of the East Wing
  • August–December 2014 — Prepare buildings for demolition of Central, Reeves and West Wings and build temporary walls to separate patient care areas from construction
  • December 2014–July 2015 — Demolition of the Central, Reeves and West wings
  • June–July 2015 — Shoring to protect the historic Moreton Bay fig tree on Pueblo St.
  • April–September 2015 — Rebuild exterior walls where South and Centennial wings converge
  • 2015–2018 — Centennial Wing expansion and construction of the additional new patient pavilion

While a large portion of the new Santa Barbara Cottage Hospital is now open and serving the community, there’s still work to be done to complete the new hospital. Part of that includes demolishing existing buildings and carefully partitioning patient care areas as the third new patient pavilion is constructed. Visit our website or scan the QR Code with your smartphone to see a 3D video animation showing how SBCH construction will progress in the coming years. Watch It on YOUtube...

 

 

 