Bella Riviera: Workforce Homes
The Workforce Homes Project at the former St. Francis Hospital site was initiated by the Santa Barbara Cottage Hospital Foundation (SBCH Foundation) as a means of providing affordable homes to meet the housing demands faced by those employed by the Cottage Health System.
|
|
|
|
The SBCH Foundation has formed an entity called the Villa Riviera Real Estate Company (VRE) to develop the newly named Bella Riviera. VREhas contracted with Irvine-based SL Residential (SLR) to build the Bella Riviera condominiums and market the units for sale.
The project consists of the demolition of the former St. Francis campus buildings and the construction of 115 townhomes on the approximately 5.9 acre site. SBCH Foundation is undertaking this project in order to provide 81 affordable homes to our employees. The homes will be built using the Santa Barbara Built-Green "3-star" rating.
Our goal is to improve CHS’s ability to attract and retain medical professionals in order to preserve the high quality of health care in the greater Santa Barbara community.The purposes and strengths of this unique project include:
- increasing the supply of quality affordable homes
- retaining existing Cottage employees
- recruiting medical professionals to our community
|
|
|
|
We want to hear from you about any concerns and questions you may have throughout this process. Our hope is that by establishing a system to deal with any issues that may arise, we can address them swiftly and competently, and maintain good neighbor relations.
|
Current work: A look ahead
(October through January)
|
| |
• |
|
On-site underground utilities |
| |
• |
|
Retaining walls at upper and lower parks |
| |
• |
|
Foundations and CMU walls at upper park |
| |
• |
|
Podium deck pour at Villas 1 and 2 |
| |
• |
|
Exterior finishes |
| |
• |
|
Concrete pours |
| |
• |
|
Lumber deliveries |
| |
• |
|
Caisson footings |
|
|
Project Timeline Summary: January 2011 – November 2012
|
| |
• |
|
January to June 2011 |
 |
Rough site grading |
| |
• |
|
January to August 2012 |
|
Off-site public works (intermittently) |
| |
• |
|
February to August 2011 |
|
Foundations |
| |
• |
|
March 2011 |
|
Begin construction |
| |
• |
|
June 2011 to November 2012 |
|
Framing to finish |
| |
• |
|
October 2011 |
|
Models open |
| |
• |
|
March 2012 to December 2012 |
|
Occupancy |
Construction Schedule
| |
Begin
Foundations
|
Begin
Framing
|
Remove Soundwall;
Landscaping
|
| Phase 1: Upper Park |
April 2011 |
June 2011
|
November 2011 |
| Phase 2: Villa I |
May 2011 |
October 2011
|
April 2012 |
| Phase 3: Villa II |
May 2011 |
November 2011
|
May 2012 |
| Phase 4: Lower Park |
July 2011 |
November 2011 |
October 2012 |
| Phase 5: Central Park |
July 2011 |
November 2011 |
October 2012 |
Contacts
11/29/11
|
|