Construction of the new Santa Barbara Cottage Hospital will fulfill the State seismic requirements of Senate Bill 1953.

September 2006
New 633-space PUEBLO PARKING STRUCTURE for patients, visitors, volunteers and physicians opens.

September 2005 - Summer 2008
Construct new ENERGY CENTER (power plant) on Junipero Street

May 2006 - June 2007
Construct UNDERGROUND DRAINAGE CULVERT AND UTILITIES in Oak Park Lane area

June 2006 - June 2007
Build new COTTAGE CHILD CARE CENTER on Castillo Street

May 2006 - July 2007
Construct new 550-space PARKING STRUCTURE behind the Knapp Building for employees

Summer 2007
Demolition of existing areas, employee parking structure and child care centers

Winter 2007 - Spring 2011
Construct NEW PLAZA, HOSPITAL ENTRANCE, TWO ACUTE CARE PAVILIONS and DIAGNOSTIC & TREATMENT PAVILION

Spring 2011 - Summer 2012
Demolition of existing buildings

Summer 2012
Begin construction of third PATIENT PAVILION.

 

May, 2008

 
Hospital Replacement Project
Neighborhood Meetings
Construction Timeline
Contact Information
About Us
   
Live Construction Cam
Construction and Parking Updates
Construction Project
Management Hotline:
569-7383
   

 

Patient Rights and Privacy Site Index Key Phone Numbers